Address: 4052 S Montgomery Ave, Chicago, IL 60632
River West Multi-Family - Project I
440 N Halsted St, Chicago, IL 60642 United States
Dining Room
Living Room
Kitchen
Entry Corridor
Bathrooms
Bedrooms
Closets
3D Mapping
Cosmetic Alterations
Paint
Proposed Scope:
​
Prep Work
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
​
- Floor protection.
- Plastic tarp.
​
​
Prime
​
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
​
- Doors
- Trim
- Interior walls
- Exterior walls
- Ceiling
- Wooden cabinets
- Kitchen water damage patch (moldicide oil-based)
- Low voltage closet patch (moldicide oil-based)
- Rear egress patch (moldicide oil-based)
​
​
Top Coat Paint
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
​
- Doors
- Trim
- Interior walls
- Exterior walls
- Ceiling
- Wooden cabinets
​
Paint Materials
- Painting tape
- 5 gallon paint
- 1 gallon moldicide primer
- Pans
​
​
Labor Estimate: $1,960.00 (ceiling)
Labor Estimate: $5,865.00 (walls, trim, doors)
​
Material Estimate: TBD
Project Term: 2-3 days (ceiling)
Project Term: 5-7days (walls, trim, doors)
​
​
​
​
Proposed Budget for Labor: $7,825.00
Proposed Budget for Parts/Materials: TBD
Proposed Budget for Fixtures: TBD
​
Total Proposed Budget: TBD
​
​
Hardwood Floor Refinishing
Proposed Scope:
​
Flooring
​
(Main bedroom, main bedroom closet 1, main bedroom closet 2, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 3, bedroom 3 closet, U-corridor, laundry room, pantry, low voltage closet, common coat closet 1, common coat closet 2)
​
- Sand
- Stain
- Varnish
​
​
Labor Estimate: $3,600.00
Material Estimate: Stain and varnish included
Project Term: 1 day
​
​
​
​
​
Proposed Budget for Labor: $3,600.00
Proposed Budget for Stain/Varnish: Included
​
Total Proposed Budget: $3,600.00
​
​
Drywall
Proposed Scope:
​
(kitchen, U-corridor, low voltage closet)
​
- Scrape, mud, sand kitchen bubble.
- Patch, mud, sand two ceiling holes.
Materials
- 1 sheet of drywall
- compound
- drywall tape
- fasteners
- sanding blocks
​
​
Labor Estimate: $350
Material Estimate: TBD
Project Term: 1 day
​
​
​
​
​
Proposed Budget for Labor: $350.00
Proposed Budget for Materials: TBD
​
Total Proposed Budget: $350.00
​
​
Structural Alterations
Proposed Scope:
​
(Dining and living room)
Prep Work
- Plastic tarp
- Floor protection
- Identify utility shutoffs
​
Demolition
- Remove drywall
- Cut back electrical conduits to remove or reroute openings.
- Remove framing
- Remove fireplace.
​
Electrical
- Remove two receptacles on dining side.
- Remove junction box on dining side.
- Remove receptacle on living room side.
- Remove junction box on living side.
- Remove fireplace ignitor switch.
​
Drywall
- Patch/finish existing header.
​
​
Labor Estimate: $2,900.00
Material Estimate: TBD
Project Term: 2-3 days
​
​
​
​
​
Proposed Budget for Labor: $2,900.00
Proposed Budget for Parts/Materials: TBD
Proposed Budget for Fixtures: TBD
​
Total Proposed Budget: TBD
​
​