Team Name: Zoe Hamburger
Reference Number: #2012809381
Table of Contents:
Contractor Name: V Development Group LLC
Address: 4052 S Montgomery Ave, Chicago, IL 60632
River West Multi-Family - Project I
440 N Halsted St, Chicago, IL 60642 United States
Dining Room



Living Room




Kitchen




Entry Corridor



Bathrooms




Bedrooms




Closets




3D Mapping




Cosmetic Alterations
Paint
Proposed Scope:
Prep Work
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
- Floor protection.
- Plastic tarp.
Prime
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
- Doors
- Trim
- Interior walls
- Exterior walls
- Ceiling
- Wooden cabinets
- Kitchen water damage patch (moldicide oil-based)
- Low voltage closet patch (moldicide oil-based)
- Rear egress patch (moldicide oil-based)
Top Coat Paint
(Main bedroom, main bedroom closet 1, main bedroom closet 2, main bedroom bath, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 2 bath, bedroom 3, bedroom 3 closet, bedroom 3 bath, U-corridor, laundry room, pantry, powder room, mechanical room*, low voltage closet, common coat closet 1, common coat closet 2)
- Doors
- Trim
- Interior walls
- Exterior walls
- Ceiling
- Wooden cabinets
Paint Materials
- Painting tape
- 5 gallon paint
- 1 gallon moldicide primer
- Pans
Labor Estimate: $1,960.00 (ceiling)
Labor Estimate: $5,865.00 (walls, trim, doors)
Material Estimate: TBD
Project Term: 2-3 days (ceiling)
Project Term: 5-7days (walls, trim, doors)
Proposed Budget for Labor: $7,825.00
Proposed Budget for Parts/Materials: TBD
Proposed Budget for Fixtures: TBD
Total Proposed Budget: TBD
Hardwood Floor Refinishing
Proposed Scope:
Flooring
(Main bedroom, main bedroom closet 1, main bedroom closet 2, living room, kitchen, dining, bedroom 2, bedroom 2 closet, bedroom 3, bedroom 3 closet, U-corridor, laundry room, pantry, low voltage closet, common coat closet 1, common coat closet 2)
- Sand
- Stain
- Varnish
Labor Estimate: $3,600.00
Material Estimate: Stain and varnish included
Project Term: 1 day
Proposed Budget for Labor: $3,600.00
Proposed Budget for Stain/Varnish: Included
Total Proposed Budget: $3,600.00
Drywall
Proposed Scope:
(kitchen, U-corridor, low voltage closet)
- Scrape, mud, sand kitchen bubble.
- Patch, mud, sand two ceiling holes.
Materials
- 1 sheet of drywall
- compound
- drywall tape
- fasteners
- sanding blocks
Labor Estimate: $350
Material Estimate: TBD
Project Term: 1 day
Proposed Budget for Labor: $350.00
Proposed Budget for Materials: TBD
Total Proposed Budget: $350.00
Structural Alterations
Proposed Scope:
(Dining and living room)
Prep Work
- Plastic tarp
- Floor protection
- Identify utility shutoffs
Demolition
- Remove drywall
- Cut back electrical conduits to remove or reroute openings.
- Remove framing
- Remove fireplace.
Electrical
- Remove two receptacles on dining side.
- Remove junction box on dining side.
- Remove receptacle on living room side.
- Remove junction box on living side.
- Remove fireplace ignitor switch.
Drywall
- Patch/finish existing header.
Labor Estimate: $2,900.00
Material Estimate: TBD
Project Term: 2-3 days
Proposed Budget for Labor: $2,900.00
Proposed Budget for Parts/Materials: TBD
Proposed Budget for Fixtures: TBD
Total Proposed Budget: TBD
Contact
Have a question about your project? Connect with your team.
Operations: Ramon Vargas
Email: ramon@vdevgroupllc.com
Phone: 773-415-7428
